Tool applicationName of the tool AMP 3 Process map Who applied the tool in the case? The tool is split into two halves, with the first half of the tool being run by the Design Manager and the second half by the Catchment manager. The decision making process is broken down further into sections and sub sections which are monitored by different members of the project team. For information on the application of this tool refer to the PETUS UK case study on Gowerton Outfall. Time taken to fully apply the tool The tool lasts the length of a project. Any other interesting information about the tool
The AMP 3 Process Map has won a number of awards including an internal award for Business Excellence. These internal company business awards are for projects or initiatives across three categories - Safety, Quality and Sustainability - which represent a significant contribution towards achievement of the group's values.
All members of the Capital Alliance team have to use the process.
Generally the process is a guide tool but it is picked up at internal audits where evidence may be asked to demonstrate that certain processes have been carried out and documented.
All sources of information are contained and referred to within the AMP3 process, including a reference to fulfil the Environmental Manual.
A key driver for the design and use of the Process Map is to achieve the International Standards of ISO 9000 (Quality), 14000 (environment) and 18000 (safety).
Case study/ies where tool is in use Gowerton Outfall |